You need to know…

What do I need to know before placing an order for my dream house?

1.       Do I have land with building permit?

2.       Geographic area of work and access to my land!

3.       Do I have the cash, or should I apply for a long-term loan?

How long does the construction process take?

–          When all licences are achieved and approved by the authorities, the land should be compacted and prepared for the foundation.

–          The production time for all materials is between 75 to 110 days. During this time the preparation and the making of the foundation should be finished and ready before the construction materials arrive.

–          The assembling and finishing of the complete house will take 15 to 20 days.

LICENSE       75 – 110 DAYS                    15 – 21 DAYS                       15 DAYS

APPROVED                                                                                                                       

REVISION / CONTROL

This means that after having the license and the signed contract it will take between 3,5 to 5 months to finish the project.

Deja una respuesta

Tu dirección de correo electrónico no será publicada. Los campos obligatorios están marcados con *

You need to know

What do I need to know before placing an order for my dream house?

1.  Do I have land with building permit?

2. Geographic area of work and access to my land!

3. Do I have the cash, or should I apply for a long-term loan?

How long does the construction process take?

–          When all licences are achieved and approved by the authorities, the land should be compacted and prepared for the foundation.

–          The production time for all materials is between 75 to 110 days. During this time the preparation and the making of the foundation should be finished and ready before the construction materials arrive.

–          The assembling and finishing of the complete house will take 15 to 20 days.

LICENSE                                75 – 110 DAYS                    15 – 21 DAYS                       15 DAYS

APPROVED                                                                                                                         REVISION / CONTROL

This means that after having the license and the signed contract it will take between 3,5 to 5 months to finish the project.